CVEA Explains Christmas Holiday Power Outages Occurring Two Weeks Ago

JANUARY 10TH, 2024  PRESS RELEASE FROM CVEA     Severe Weather Continued in the Copper Basin  Causing Multiple Power Outages Over the Christ...

JANUARY 10TH, 2024 
PRESS RELEASE FROM CVEA  

 Severe Weather Continued in the Copper Basin 

Causing Multiple Power Outages Over the Christmas Holiday 

Broken Pole At Mile 6.5 On The Edgerton (Photo, CVEA) 


Glennallen, AK – A second round of severe weather struck CVEA’s Copper Basin district over the Christmas holiday, resulting in multiple power outages beginning Saturday evening, December 23, and lasting until 6:30 p.m., December 25. Outages were experienced in various locations along the Richardson, Old Rich, Edgerton, and Glenn Highways. At one point, the district experienced outages in as many as nine locations simultaneously. 


Wet, heavy snow was the ongoing cause of outages experienced by CVEA members. Heavy snow caused trees to bend or break and fall into power lines, causing damage to the lines and extensive damage to other equipment. Hazardous road conditions impacted the crew’s ability to travel and patrol, and increased the time it took for repairs and power restoration. 


Due to avalanche conditions, Thompson Pass closed early Sunday morning, preventing the Valdez line crew from assisting. CVEA secured extra line crew members from Electric Power Constructors in the Mat-Su Valley. They arrived on scene by roughly 10:30 a.m. Sunday. Once the highway reopened late Sunday evening, the Valdez line crew joined the restoration effort. 


Crews worked around the clock throughout the duration of this weather event patrolling the lines, clearing trees from the lines, and making necessary equipment repairs. Areas were re-energized systematically based on several factors, including the number of people affected, length of travel to the area, and significance of the repairs needed. It is always the priority of CVEA to restore power to the greatest number of members in the shortest length of time possible, lessening the impact to the majority. 


During the outage, CVEA received questions and heard concerns regarding the number of trees that have fallen onto the lines and caused damage. This is an issue that CVEA works hard to combat each year through an extensive right of way management program, and planned system improvements. Annual focus is given to areas identified as trouble spots, or areas that have experienced an unusually high number of outages or damage due to trees. From there, focus shifts to the main line as that serves the largest number of members, then to lines that feed smaller areas, such as subdivisions and side roads. 


Right of way management is ongoing and a significant amount of time and funds are spent on this effort each year. Annually, CVEA clears 12 miles of transmission right of way and 31 line-miles of distribution, with 20 of those miles in the Copper Basin and 11 in Valdez. In addition, crews tackle trouble spots with the SkyTrim. In 2022 and 2023, crews trimmed roughly 26 miles on the West Line, the entire Old Edgerton Highway, and 14 miles on the Edgerton Highway, respectively. In 2024, CVEA will continue work on the West Line, trim trouble areas from 

Related

Community Info 8154551164328325083

Click Here For Front Page

Too Far North

Too Far North

Check Road Conditions Here

Check Road Conditions Here
Click On 511 Site

CLICK: TAKE A BREAK

CLICK: TAKE A BREAK
Read The Bearfoot Guide To Roadside Alaska

Today's Top Journal Stories

Search For Somebody Below

See Every Single Story

The Journal Is Copyrighted Material

The Journal Is Copyrighted Material
All rights reserved. Contact us at 907-320-1145 or write: Linda.ncountry@gci.net
item